Tanzania 1200t/d gold concentrator

2016-02-23

Tanzania 1200tpd gold concentrator installation project has been completed and put into operation. In the installation process, work rigorous, hard working, in a short period of time to accomplish the work, plant production line reached the expected recovery rate, won high praise from customers.
Project Overview
Tanzania 1200t/d mineral processing plant, located in Africa, in the aspects of project management, construction technology, resource supply and coordination are different from domestic.
Mainly for the dense, leaching, desorption electrolysis and other aspects of the installation and commissioning work mainly includes three aspects:
1, dense, leaching, desorption electrolysis and other mechanical equipment installation;
2, process piping, operating platform installation (excluding outdoor tailings pipeline);
3, electric power, water supply and drainage (excluding water supply)
Mineral Processing
The core technology of the project for the whole mud cyanidation of gold ore, mainly for sulfide ore and oxide ore two.
The core technology of the project:
The core technology of the project for the whole mud cyanidation of gold ore, mainly for sulfide ore and oxide ore two.
Oxidized ore grade 2.4g/t, gold only price for recovery of elements, all sliming cyanidation gold extraction scheme can get gold leaching rate was 93.75%;
Gold bearing sulfide ore 10.7g/t, gold only price for recovery of elements, all sliming cyanidation gold extraction scheme can get gold leaching rate was 91.58%.
civil construction
Civil construction mainly involves two parts of plant and equipment foundation. Thickener, bath in the equipment to complete the infrastructure work, and installation of construction equipment pipelines, electrical instrument connection.
Plant construction workshop construction workshop construction workshop construction workshop construction workshop construction
In Africa for outdoor work need to pay attention to sunscreen and anti mosquito bites, so even if the sweltering heat, loading ore field staff to wrapped himself tightly, very hard.
Bath and thickener installation
Leaching tank lifting. Most of the leaching tank, thickener and other equipment are thin walled tank hoisting, so, transportation prevent non-standard equipment of the deformation is one of the difficulties. For large diameter tank mines used in domestic slice production, methods and installation site. For the smaller diameter of the tank, the construction site has produced a special hanger with lifting, to ensure the quality.